EPC

Terang BESS 100MW/200MWh

TEC-C delivered Balance-of-Plant (BOP) works for 100MW/200MWh BESS and the  EPC works for the 120MVA 220/33kV substation grid connection infrastructure safely, coordinating construction and commissioning in a congested, footprint-constrained environment.

Quick facts

  • Asset Owner: FRV
  • Client: Canadian Solar
  • Location: Terang, VIC
  • BESS size: 100MW / 200MWh
  • Grid connection substation: 120MVA 220/33kV
  • TEC-C scope: BESS balance-of-plant installation works and complete EPC delivery of the 220/33kV substation

Approach

TEC-C delivered balance-of-plant installation works for the 100MW/200MWh Terang BESS and completed EPC delivery of the new 120MVA 220/33kV substation to enable connection into the AusNet Transmission network.

 

To maintain programme certainty through construction and commissioning, TEC-C coordinated delivery across multiple work fronts, aligning installation sequencing, logistics and subcontractor activities. In parallel, TEC-C supported critical interface requirements including the AEMO 5.3.9 connection pathway for a new inverter model and planning compliance updates for the final layout, reducing approval-driven rework and avoiding delays to commissioning activities.

 

The project required careful planning and sequencing due to a tight site footprint, a physically congested connection environment, and noise and layout constraints that needed to be managed without compromising programme or safety outcomes.

 

TEC-C’s delivery approach was designed to keep the project advancing safely and efficiently, including early cable installation where practical, disciplined workface coordination, and construction sequencing that supported continuous progress even within a very constrained footprint.

 

Outcome: Works were coordinated across the BESS and substation areas to support a smooth transition from construction into testing and commissioning.

Terang Construction

Key features:

  • Balance-of-Plant (BOP) installation works for a 100MW / 200MWh BESS
  • Complete EPC delivery of a 120MVA 220/33kV grid connection substation
  • Interface coordination supporting commissioning readiness, including alignment with AEMO 5.3.9 requirements and AusNet Services integration
  • Delivery planning for a tight footprint and congested HV interface environment, with logistics and sequencing designed to maintain programme certainty
  • Multi-front construction approach supporting safe, efficient progress through installation and commissioning activities